ADU rules are the same statewide floor in every California city, and each city adds its own layer on top of that floor. This table compares the Orange County and Los Angeles area cities L Square Design & Build builds in: who reviews your plan, whether the city posts pre-approved designs, and the one local factor that decides your timeline.
What ADU rules are the same in every California city?
Every California city applies the same floor to an ADU permit. The application is considered and approved ministerially, with no discretionary review and no hearing (California Government Code 66317).
Since January 1, 2026 the city has 15 business days to tell you whether your application is complete, and if it calls the file incomplete it has to hand you a list of the missing items and a description of how to cure them. If the city misses that deadline, the application is deemed complete (California Government Code 66317).
Once the file is complete the city has 60 days to approve or deny it, and if it does not decide inside that window the application is deemed approved. The same 60-day clock applies to every city on this list, which is why the differences you read below are about process, not permission (California Government Code 66317).
How large can an ADU be in any California city?
A city may not set a maximum size below 850 square feet of interior livable space, or 1,000 square feet for a unit with more than one bedroom (California Government Code 66321).
A city also has to allow at least 800 square feet with four-foot side and rear setbacks, so your lot limits the project before the counter does (California Government Code 66321).
A detached ADU is capped at 1,200 square feet of total floor area, and an attached ADU may not exceed 50 percent of the existing primary dwelling (California Government Code 66314).
Which Orange County cities have pre-approved ADU plans?

Seven of the Orange County cities we work in publish plans a homeowner can use instead of commissioning drawings from scratch. A pre-approved set is a head start on design, not a finished project: your foundation, utility routing and setbacks still have to be designed for your lot.
The program differs by city. Anaheim runs ADU Express with one-day permitting for eligible new detached units, Santa Ana reviews a complete over-the-counter application in one track, Garden Grove's program is called ADU Go, Westminster is explicit that its plans are pre-approved but not pre-permitted, Huntington Beach publishes a single plan of 490 square feet that cannot be modified, Costa Mesa offers pre-engineered designs, and Irvine operates its own program for qualifying lots.
Read the city's own page before you download anything: Anaheim, Santa Ana, Garden Grove, Westminster, Huntington Beach, Costa Mesa and Irvine each publish their own program details, and the California ADU laws guide explains the state rule behind them.
| City | Who reviews | Pre-approved plans? | The local factor that matters |
|---|---|---|---|
| Irvine | Own counter | Yes, city Pre-Approved ADU Plans Program | The HOA review runs parallel to the city permit, and the HOA letter usually sets your start date |
| Santa Ana | Own counter | Yes, over-the-counter pre-approved track | Older housing stock, so garage slab condition and panel capacity decide conversion budgets |
| Anaheim | Own counter | Yes, ADU Express catalogue | One of the faster OC plan checks in our experience (about 4 weeks on clean submittals) |
| Costa Mesa | Own counter | Yes, pre-engineered designs | Standard state-law path, the lot rather than the counter decides the project |
| Huntington Beach | Own counter | Yes, one 490 square foot plan with no modifications allowed | Standard path, and wide postwar lots suit detached units |
| Newport Beach | Own counter | No | Slower plan check (10+ weeks is common), so budget the calendar, not just the build |
| Tustin | Own counter | No | Standard state-law path |
| Fullerton | Own counter | No | Standard path, and older stock rewards a slab-and-panel check before quoting |
| Garden Grove | Own counter | Yes, ADU Go (active since Jan 2025) | City publishes official ADU handouts in English, Vietnamese and Spanish |
| Orange | Own counter | No | Four historic districts, so ADUs there need a preservation professional's report and design review |
| Mission Viejo | Own counter (administrative, no neighbor notice) | No | HOA architectural review runs in parallel, and hillside lots make slope the budget factor |
| Buena Park | Own counter | No | Standard state path, no exotic local wrinkles, the property decides |
| Westminster | Own counter and online submittal portal | Yes, standard plans (pre-approved, not pre-permitted) | City is explicit that full plan check still applies to pre-approved plans |
| Fountain Valley | Own counter | No | Published development-standards handout, and flat tract lots |
Which Los Angeles area cities have pre-approved ADU plans?
Four of the Los Angeles area cities we work in publish usable plan sets: the City of Los Angeles through LADBS, Long Beach through its PAADU catalogue, Lakewood through a posted program you file through the Planning Portal, and Whittier with four plans that run from a small studio to a two-bedroom.
Two more cities are working on a program without anything posted yet. Torrance is accepting designer-owned plans for pre-approval and Cerritos is accepting submissions of its own, so there is nothing on the shelf to pick from today in either city. Downey has a pre-approval program and no approved plans as of July 2026, and Pasadena's city plans expired at the end of 2025, so Pasadena is a custom design city for now.
The California ADU laws guide and the Orange County permit guide cover the state rules these city programs sit on top of.
| City | Who reviews | Pre-approved plans? | The local factor that matters |
|---|---|---|---|
| City of LA | LADBS plus LA City Planning (LA County if unincorporated) | Yes, LA standard plans | Hillside, coastal and older-home conditions move timelines, not the review clock |
| Long Beach | Own counter | Yes, PAADU catalog (active) | A qualifying catalog design can trim design cost |
| Pasadena | Own counter | Expired (standard plans ended Dec 2025) | Budget for custom design |
| Torrance | Own counter | No, program accepting submissions | Suburban lots suit detached units and conversions |
| Whittier | Own counter | Yes, four plans | Older homes and generous lots, so slab and panel checks come first |
| Downey | Own counter plus Fire Department review | Program exists, no plans posted yet (as of Jul 2026) | Downey Fire publishes its own ADU fire-plan guide, so design to it up front |
| Norwalk | Own counter | No | City publishes a 2026 ADU guidebook and submittal checklist, so file it complete and the clock starts |
| Lakewood | Own counter (online portal) | Yes, active AB 1332 program | Two budget lines people miss: school fees paid at the district, and the Construction of Dwelling Unit Tax |
| Cerritos | Own counter | No, program accepting submissions | Step-by-step published process and posted construction hours, so complete submittals matter |
How long does plan check take in each city?
Plan check time is the practical difference between these counters. The ranges below are our own project experience, so treat them as a range and confirm the current number when you file.
Speed only helps if the file is complete. A clean submittal moves through review in the shortest window, while an incomplete package resets the queue in every city on this list, which is why submittal quality matters more than the city you are in.
The ADU timeline guide turns the review clocks into calendar time for a whole project, from first sketch to final inspection.
| City | Plan check | The other question the city asks |
|---|---|---|
| Anaheim | about 4 weeks on a clean submittal | Does the ADU Express catalogue fit your lot |
| Costa Mesa | five to seven weeks | Is a pre-engineered design enough for the household |
| Huntington Beach | six to eight weeks | Is the lot inside the coastal zone |
| Newport Beach | 10 weeks or more | Will the exterior pass design review |
| Tustin | five to six weeks | Book the pre-application meeting first |
Which cities add a second reviewer on top of the city counter?
Three layers of review sit on top of the state clock in this region, and each one is a design constraint you should know before you draw.
HOA review is the first. In Irvine the village associations run design review on materials, colors, roof lines and sometimes placement, and in Mission Viejo the association runs its own architectural committee alongside the city review.
Historic review is the second. Orange has four historic districts, and inside one the city asks for a preservation professional's report before plan check, while Pasadena carries landmark and historic district review on top of an ordinary permit.
Fire and coastal review are the third. Downey runs a separate Fire Department review of access, sprinklers, egress and smoke alarms, Whittier requires a fire flow approval and a sewer lateral inspection for every ADU, and Huntington Beach can add a coastal development permit on top of the city permit.
Do ADU rules really differ from city to city?
The approval floor is identical statewide, and the differences are a second layer, not a different standard. Three patterns explain most of what you see in the tables above.
Pre-approved programs are spreading unevenly. Some cities publish downloadable plans, some publish designer-owned plans, some run a program with nothing posted yet, and one city lets a plan pre-approved by another agency count. Where a program exists, it shortens design time and nothing else.
The second reviewer is the real variable. HOAs, historic districts, fire departments and coastal zones do not decide whether your ADU is legal, but designing around them from day one is the difference between approval and correction rounds.
State law is the floor in every city. The city shapes how it reviews, not whether a code-compliant unit is approved. The California ADU laws guide sets out the sections this table leans on.
What can your lot allow?
Send your address for a site-specific ADU feasibility review and estimate.
What do impact fees and utility charges look like?
No impact fee applies to an ADU of 750 square feet of interior livable space or less, and the same exemption applies to a junior ADU of 500 square feet or less. Above that line, impact fees are charged proportionately in relation to the square footage of the primary dwelling (California Government Code 66311.5).
Utility charges follow a separate rule. An ADU is generally not treated as a new residential use when a water or sewer connection fee or capacity charge is calculated, unless the unit was built together with a new single-family dwelling (California Government Code 66311.5).
City fee lists still add their own lines. Lakewood's published list includes school fees paid directly at the school district and the city's Construction of Dwelling Unit Tax, and the ADU cost guide shows how those line items land in a project total.
Do I need parking for an ADU?
Required parking for an ADU cannot exceed one space per ADU or per bedroom, whichever is less, and tandem parking on a driveway is allowed (California Government Code 66314).
The exemptions are broad. No parking standard applies when the unit sits within one-half of one mile walking distance of public transit, when it is part of the primary residence or an accessory structure, when the lot is inside a historic district, or when a car share vehicle is within one block (California Government Code 66322).
One more rule matters on older lots: when parking spaces are demolished to build the unit, the city cannot require those spaces to be replaced (California Government Code 66314).
Can I rent an ADU separately from my house?
An ADU may be rented separate from the primary residence. It may not be sold or otherwise conveyed separate from the primary residence, with an exception set out in Article 4 of the same chapter of the Government Code (California Government Code 66314).
That is the rule most homeowners ask about when they plan to add a unit for a family member, and it is also why a junior ADU created inside the existing home carries a recorded deed restriction.
What should I check before I hire a contractor?

Check the property before you check the price. Slope, side-yard access, utility capacity, flood zone, historic district status and any HOA covenant are site facts that a site visit establishes, and each one changes the design rather than the budget.
Check the city path next. Ask which counter reviews your plan, whether a pre-approved design fits your lot, and what the city publishes about submittals, then match the design to that path instead of filing and correcting.
The ADU construction process checklist places each step in the schedule, and the ADU design ideas for Orange County lots shows how footprint, daylight and privacy trade against each other before drawings are commissioned.
Where can I read each city's own ADU rules?
We maintain a guide for every city in this table, and the city page is the authority for the local program: Irvine, Santa Ana, Anaheim, Costa Mesa, Huntington Beach, Newport Beach, Tustin, Fullerton, Garden Grove, Orange, Mission Viejo, Buena Park, Westminster and Fountain Valley for Orange County, and Los Angeles, Long Beach, Pasadena, Torrance, Whittier, Downey, Norwalk, Lakewood and Cerritos for the Los Angeles area.
This table is compiled from each city's official ADU pages and our own permit-counter experience, and we update it as programs change. It is free to cite with attribution and a link back to this page. Corrections are welcome on (949) 374-7980.
What does the state plan pre-approval program change?
State law requires every city and county to run a program for pre-approving ADU plans, and a detached ADU filed on a plan the agency pre-approved in the current building code cycle has to be approved or denied within 30 days (California Government Code, plan pre-approval program).
A pre-approved set replaces the drawings for the unit itself. You still supply a site plan, energy and structural documents, a foundation that suits your soil, and a licensed builder (California Department of Housing and Community Development, Accessory Dwelling Units program).
Agencies may also accept plans pre-approved by another agency in California, and they post the plans they have approved. If your parcel is outside city limits, the county's own pre-approval program applies instead of a city one.
Project evidence
- L Square Design and Build ADU project examples photographed in Orange County and Los Angeles County. Project evidence
- A finished detached ADU in Pasadena with a vaulted ceiling over an open kitchen and living area, designed and built by L Square Design and Build. Project evidence
- A detached two story ADU in Rosemead with bedrooms, bathrooms, a loft and a private balcony, designed and built by L Square Design and Build. Project evidence
Related L Square guides
- California ADU laws explained
- Orange County ADU permit requirements
- How long an ADU takes in Orange County
- ADU cost guide for Orange County
- ADU construction process checklist
- ADU design ideas for Orange County lots
- ADU construction examples from L Square projects
- Irvine ADU guide
- Huntington Beach ADU guide
- Anaheim ADU guide
Authoritative sources
- California Government Code Section 66317, ADU application completeness and decision timelines — California Legislative Information
- California Government Code Section 66321, ADU size, setback and height standards — California Legislative Information
- California Government Code Section 66314, ADU approvals, floor area and parking standards — California Legislative Information
- California Government Code Section 66311.5, ADU and JADU impact fees and utility connection charges — California Legislative Information
- California Government Code Section 66322, parking standards that do not apply to an accessory dwelling unit — California Legislative Information
- California Government Code Section 65852.27, local agency program for pre-approval of accessory dwelling unit plans — California Legislative Information
- California Civil Code Section 4751, limits on homeowner association restrictions on accessory dwelling units — California Legislative Information
- Accessory Dwelling Units program page and ADU Handbook — California Department of Housing and Community Development
Frequently asked questions
Which Orange County cities have pre-approved ADU plans?
Seven do: Anaheim through its ADU Express catalogue, Santa Ana through its over-the-counter track, Garden Grove through ADU Go, Westminster with standard plans that are pre-approved but not pre-permitted, Huntington Beach with one plan of 490 square feet that cannot be modified, Costa Mesa with pre-engineered designs, and Irvine with its own program for qualifying lots.
Do ADU rules really differ city by city?
The approval floor is identical statewide and each city adds its own review path on top. What differs is the second layer: HOA design review, historic district review, fire department review, coastal permits, pre-approved plan programs and the pace of each counter.
Which city is fastest for an ADU permit?
Anaheim is among the fastest counters we work with, and its ADU Express catalogue can clear in as little as one day for eligible new detached units. Newport Beach runs the longest plan check among the big Orange County cities because design review sits on top of plan check.
How long does a city have to decide an ADU application?
60 days from the date the city receives a completed application. If the city has not approved or denied the application within that window, the application is deemed approved (California Government Code 66317).
When does the city have to tell me my application is incomplete?
Within 15 business days of receiving the application. If the city calls the file incomplete it must give you a list of the missing items and how to cure them, and if it misses that deadline the application is deemed complete (California Government Code 66317).
Do I pay impact fees for an ADU?
No impact fee applies to an ADU of 750 square feet of interior livable space or less, and the same exemption applies to a junior ADU of 500 square feet or less. Above 750 square feet, impact fees are charged proportionately in relation to the square footage of the primary dwelling (California Government Code 66311.5).
Do I need parking for an ADU?
Required parking cannot exceed one space per ADU or per bedroom, whichever is less, and tandem parking on a driveway is allowed. No parking standard applies when the unit sits within one-half of one mile walking distance of public transit, when it is part of the primary residence or an accessory structure, or when a car share vehicle is within one block (California Government Code 66314 and 66322).
Can I build an ADU in a historic district?
Yes, but the review path changes. Orange asks for a preservation professional's report before plan check inside its four historic districts, and converted space inside the existing house is the simplest route in a historic district. Pasadena's historic district and landmark properties carry their own design review on top.
Does my HOA have to approve my ADU?
State law stops an HOA from prohibiting an ADU outright, but it can still review materials, colors and roof lines, and it runs on its own calendar. In Irvine the HOA letter usually decides your real start date, so the HOA submittal belongs in the same package as the city application.
How large can an ADU be in California?
A detached ADU can reach 1,200 square feet of total floor area, and a city cannot cap a unit below 850 square feet of interior livable space, or 1,000 square feet for a unit with more than one bedroom. Your lot, not the counter, is what usually limits the project (California Government Code 66314 and 66321).
Can I rent an ADU separately from my house?
Yes, an ADU may be rented separate from the primary residence. It may not be sold or otherwise conveyed separate from the primary residence, with an exception set out in Article 4 of the same chapter of the Government Code (California Government Code 66314).
Which rules should I read for my address?
Start with your city page, since the city runs the counter and publishes the program. Then read the state floor in the California ADU laws guide and the Orange County permit guide. If your parcel is outside city limits, the county's ADU page applies instead of a city one.