Los Angeles ADU Permit Tracker
Every ADU permit the City of Los Angeles issues on a single-family or two-family lot, counted from the city’s own open data and refreshed each month: how many, how long they take, and which neighborhoods are building.
The City of Los Angeles issued 5,971 ADU permits on single-family and two-family lots from November 1, 2025 to October 31, 2026, for 5,474 properties. That is down 9.4% from 6,592 in the prior 12 months. The median permit took 116 days from application to issue: 154 days for new construction and 68 days to convert existing space. The San Fernando Valley accounted for 54.9% of all permits.
The numbers at a glance
| ADU permits, last 12 months | 5,971, down 9.4% year over year |
| Properties | 5,474 (some projects need more than one permit) |
| Latest month | October 2026: 538 permits |
| Median time to permit | 116 days from application to issue |
| Junior ADU permits | 780, 13.1% of the total |
| Busiest planning area | South Valley, 1,700 permits |
| Source | City of Los Angeles, LADBS Building Permits open data (LADBS) |
Are ADU permits in Los Angeles going up or down?
Down, gently. The city issued 5,971 ADU permits in the latest 12 months against 6,592 the year before, a change of -9.4%. Over the last 12 months, monthly volume stayed between 469 and 538 permits. The chart shows the last 36 months; the darker bar is October 2026.
Source: City of Los Angeles, LADBS Building Permits open data, permits issued November 1, 2025 to October 31, 2026; monthly counts by issue date. Dataset refreshed November 1, 2026; queried November 4, 2026.
How long does an ADU permit take in the City of Los Angeles?
The median permit took 116 days, about 17 weeks, from the day the application was filed to the day LADBS issued it. The type of work makes the biggest difference. New construction, which covers detached ADUs, took 154 days. Converting space that already exists, such as a garage, took 68 days.
| Type of ADU work | Permits | Share | Median days to permit | Median ADU size |
|---|---|---|---|---|
| New construction | 1,882 | 31.5% | 154 days | 805 sq ft |
| Addition to an existing building | 1,968 | 33.0% | 130 days | 702 sq ft |
| Alteration of existing space | 2,121 | 35.5% | 68 days | 367 sq ft |
The plan check route LADBS assigns tells the same story: projects reviewed at the counter were issued much sooner than projects sent to regular plan check.
| Plan check route | Permits | Median days to permit |
|---|---|---|
| Expanded Counter Plan Check | 3,103 | 80 days |
| Regular Plan Check | 2,456 | 175 days |
| Plan Check at Counter | 406 | 28 days |
Source: City of Los Angeles, LADBS Building Permits open data, permits issued November 1, 2025 to October 31, 2026; days from submitted date to issue date. Dataset refreshed November 1, 2026; queried November 4, 2026.
Where in Los Angeles are ADUs being permitted?
Mostly in the Valley. The South Valley and North Valley planning areas together issued 3,277 permits, 54.9% of the city total.
At the neighborhood level, these ten community plan areas issued the most ADU permits:
| Community plan area | ADU permits |
|---|---|
| Canoga Park-West Hills-Winnetka-Woodland Hills | 475 |
| Reseda - West Van Nuys | 376 |
| Brentwood - Pacific Palisades | 370 |
| Northeast Los Angeles | 351 |
| South Los Angeles | 302 |
| Van Nuys - North Sherman Oaks | 268 |
| Mission Hills - Panorama City - North Hills | 254 |
| Granada Hills - Knollwood | 246 |
| North Hollywood - Valley Village | 243 |
| West Adams - Baldwin Hills - Leimert | 238 |
And the ten busiest ZIP codes:
| ZIP code | ADU permits |
|---|---|
| 90272 | 305 |
| 91335 | 246 |
| 91344 | 214 |
| 91331 | 212 |
| 91342 | 157 |
| 91306 | 146 |
| 91343 | 138 |
| 91367 | 134 |
| 90066 | 132 |
| 91406 | 130 |
Source: City of Los Angeles, LADBS Building Permits open data, permits issued November 1, 2025 to October 31, 2026; LADBS area planning commission and community plan area fields. Dataset refreshed November 1, 2026; queried November 4, 2026.
Wildfire rebuilds. 287 of the permits describe the work as part of a 2025 wildfire rebuild, all of them in Brentwood - Pacific Palisades. They are counted here because they are real ADU permits, but rebuilds run under emergency orders, so they are not a guide to ordinary timelines elsewhere in the city.
How should you read these numbers?
Four limits are worth knowing before you quote any of this.
- Permits, not units. One project can need several permits, for example a supplemental permit to revise plans. That is why the page shows both permits (5,971) and properties (5,474). A permit can also lapse before anything is built.
- The clock includes the owner’s time. Days to permit run from the filing date to the issue date. Time spent answering plan check corrections is inside that number, so a well prepared set of plans can beat the median.
- City of Los Angeles only. Long Beach, Pasadena, Glendale, Torrance and the other cities of Los Angeles County run their own building departments and are not in this data. For county-wide and statewide counts see our California ADU statistics.
- Single-family and two-family lots only. ADUs added to apartment buildings are a different product and are left out.
Check it yourself. The source is the City of Los Angeles LADBS Building Permits open data, published by the Department of Building and Safety. This page counts permits flagged as adding or changing an ADU or Junior ADU, with a permit sub-type of 1 or 2 family dwelling, by issue date.
Using this data. You may quote or reuse this summary with credit and a link to L Square Design & Build, under CC BY 4.0. The underlying permit records come from the City of Los Angeles.
What do the numbers mean if you own a home in Los Angeles?
Three things. First, the process works at volume: roughly 498 ADU permits a month means LADBS plan checkers see projects like yours every day. Second, plan for about 22 weeks of permitting on a detached ADU and about 10 weeks on a conversion, then add construction time. Third, because correction rounds sit inside those numbers, a complete plan set and fast answers to plan check comments are the parts of the wait an owner can control. For the city’s rules see our Los Angeles ADU guide, and for the full schedule from design to move-in see how long an ADU takes.
Frequently asked questions
How many ADU permits does the City of Los Angeles issue?
How long does it take to get an ADU permit in Los Angeles?
What is the fastest way to get an ADU permit in Los Angeles?
Where in Los Angeles are the most ADUs being permitted?
Does this data include Junior ADUs and garage conversions?
How often is the Los Angeles ADU permit tracker updated?
Check what your property allows
Tell us your city and address, we’ll come back with what your lot allows and a free estimate.
Ready to price
your ADU?
Get a free, no-pressure site evaluation from a licensed design-build team, serving Orange County & Los Angeles.