ADU Builder in Malibu, CA: City Rules, Fees and Timeline
Building an ADU in Malibu means a city permit under the city's rewritten ADU chapter, a decision within 60 days of a complete application, and L Square prefab unit prices from $180,000 to $354,000. Call (949) 374-7980.
What are the ADU rules in Malibu?
Malibu regulates ADUs in Chapter 17.44 of the Malibu Municipal Code and in Section 3.6(N)(1) of the Local Implementation Plan. The city rewrote the chapter with Ordinance No. 535, adopted June 22, 2026, which implements the state ADU statutes and adds a reduced setback provision for ADUs attached to fire rebuild structures on beachfront parcels. Malibu splits review into Class 1 units, which are statutorily regulated, and Class 2 units, which the city regulates locally. A Class 1 limited detached new build is allowed with four foot side and rear setbacks and 800 square feet or smaller of total floor area. A Class 2 unit can reach 1,000 square feet of floor area, and an attached unit is limited to 50 percent of the existing primary dwelling, though no standard may push it below 800 square feet of interior livable space. A junior ADU cannot be larger than 500 square feet. Height is 16 feet for most units, 18 feet for a detached unit within one-half mile walking distance of a major transit stop, up to 20 feet where the roof pitch matches the primary dwelling, and 25 feet for an attached unit. A Class 2 unit must sit at least four feet off a side or rear property line, and the front yard on a non beachfront lot is 20 percent of the lot depth or 65 feet, whichever is less. Total lot floor area ratio may not go past 38 percent.
How long does it take to get an ADU permit in Malibu?
Under Municipal Code Section 17.44.070 the city tells you in writing within 15 business days whether your application is complete, and it must approve or deny a complete application within 60 days of receiving it. If the city does not act in that window, the application is deemed approved. An ADU permit is approved ministerially by the community development director, so there is no Planning Commission hearing. A denial has to list the deficient items and how to fix them, and you can appeal to the planning commission, which must issue a final written decision within 60 business days. A demolition permit for a detached garage that is being replaced by an ADU is reviewed with the ADU application and issued at the same time. On the counter side, you submit through the city Development Portal, planning approval comes before building plan check, and you pay fees through the portal once staff has reviewed your documents.
What fees does the City of Malibu charge for an ADU?
The city adopted a new fee schedule for fiscal year 2026-27. It lists administrative plan review at $3,527 for Level 4, minor review, and $7,344 for Level 5, major review. A Level 3 coastal development permit, the level that covers accessory structures and second units, is $13,244. Plan check for all new residential construction, which includes additions, is $2.48 per square foot, and the building permit is $2.51 per square foot. On impact fees, Municipal Code Section 17.44.100 bars any impact fee for an ADU under 750 square feet of interior livable space, and any impact fee above that size must be charged in proportion to the floor area of the primary dwelling. A junior ADU or an ADU under 500 square feet does not add assessable space for school fees under Education Code section 17620. Utilities are separate. A converted ADU needs no new utility connection and no connection fee unless it is built with a new single family home, while other ADUs need a new separate connection with a charge capped at the reasonable cost of the service.
How much does an ADU cost in Malibu?
L Square publishes configured prefab unit prices the same way for every project: $180,000 for Model 600, $240,000 for Models 800A and 800B, $295,000 for Models 1000A and 1000B, and $354,000 for Model 1200. Those are unit prices, not a final project total for a specific house. A Malibu quote also carries the site work that the lot needs, such as utility connections and trenching, grading on a sloped pad, drainage work, retaining work and structural engineering. Coastal parcels and parcels that burned in the Woolsey or Palisades fires carry extra review, so the scope has to be written against the actual property. City fees, plan check and any impact fee are separate line items from the unit price, and the written proposal should list them.
What should I check before building an ADU in Malibu?
Malibu sits entirely inside the California Coastal Zone with a certified Local Coastal Program, so a coastal permit may be part of the review. Check the fire route as well. The city is in a Very High Fire Hazard Severity Zone, Los Angeles County Fire enforces apparatus access, and Municipal Code Section 17.44.050 says those fire code requirements may not be used as a zoning based reason to deny an ADU that state law requires to be approved ministerially. On the survey, confirm the four foot side and rear setback and the front yard distance for your lot. On utilities, plan for a new separate water and sewer connection with a capacity charge if you are not converting existing space. If the unit will connect to an on-site treatment system, the application needs a percolation test completed within the last five years, or recertified within the last 10 years. If the lot burned in the Woolsey or Palisades fires, the city rebuild deadlines apply: Planning Verification approvals expire eight years from the date of the Woolsey Fire, building permits had to be obtained by November 8, 2026, and fee waiver eligibility ended when all required building permits had to be pulled by December 30, 2026.
Official Malibu ADU sources
- The City of Malibu page for Accessory Dwelling Units states that the city's ADU regulations are codified in Malibu Municipal Code 17.44 and Local Implementation Plan Section 3.6(N)(1), that Malibu lies entirely within the California Coastal Zone with a certified Local Coastal Program, and that on June 22, 2026 the City Council adopted Ordinance No. 535 approving Zoning Text Amendment No. 25-003 to update the ADU regulations. The page also records a California Coastal Commission comment letter dated March 19, 2024. Official source
- Ordinance No. 535 amends Malibu Municipal Code Title 17. Section 17.44.060 splits review into Class 1 statutorily regulated ADUs approved under Government Code Section 66323 and Class 2 locally regulated ADUs, and allows one detached new build on a single family lot with side and rear setbacks of at least four feet and a total floor area of 800 square feet or smaller. Section 17.44.070 requires a completeness determination within 15 business days, ministerial approval by the community development director, and a decision within 60 days of a complete application. Official source
- The City of Malibu adopted FY 2026-27 fee schedule lists administrative plan review at $3,527 for Level 4, minor, and $7,344 for Level 5, major. It lists the Level 3 Coastal Development Permit, covering accessory structures, 2nd units and additions, at $13,244. For all new residential construction including additions it lists plan check at $2.48 per square foot and permit at $2.51 per square foot. Official source
- HCD issued written findings on November 13, 2024 under Government Code section 66326 that Malibu ADU Ordinance No. 511, adopted January 8, 2024, does not comply with state ADU law, and listed ten numbered deficiencies, including outdated statutory numbering after SB 477, a 20 foot minimum street width for ingress and egress, a prohibition on attached ADUs on multifamily lots, deed restrictions, a 16 foot height cap, and an attached size limit that conflicts with Government Code section 66321. The city had 30 days to respond, no later than December 13, 2024. Official source
- The City of Malibu Planning Department page states that Planning and Building Safety staff use an Online Development Portal to submit projects, view status updates and manage documents and fees. It describes a Planning phase first, where an applicant registers the project, uploads a preliminary set of plans, receives a submittal checklist, pays fees through the portal and is routed to reviewing departments, and then a Building phase, where planning approval comes before Building Safety and building plan check is submitted through the portal with plan check in the project description. Official source
- The City of Malibu Woolsey Fire Rebuilds fee waiver and deadlines page states that Planning Verification approvals expire eight years from the date of the Woolsey Fire and that property owners have until November 8, 2026 to obtain building permits, with time extension requests due before that date. It also states that all required building permits must be pulled by December 30, 2026, that no fees will be waived after December 30, 2026, and that fee waiver applications and complete Planning Department applications were due by June 30, 2026. Official source
What can your Malibu lot allow?
Send your address for a site-specific ADU feasibility review and estimate.
Malibu ADU questions
Does Malibu's ADU ordinance comply with California law?
How tall can an ADU be in Malibu?
How big can an ADU be in Malibu?
Do I need to provide parking for an ADU in Malibu?
Can I rent an ADU in Malibu on a short term lease?
What does the City of Malibu charge to process an ADU permit?